A company wants to build a large AI data centre in Sabah, a Malaysian state on the island of Borneo where water and electricity are already in short supply.
Its pitch: the centre would make all its own power and cool its servers with treated seawater, so it would not need public water for cooling. Chinese firms would build and equip much of it.
But the agreements signed so far are not state approval.
Early agreements, not approval
The developer, North AIDC, signed preliminary agreements with seven partners on 12 November for a 130-megawatt facility near the state capital, Kota Kinabalu, Warta Oriental reported.
Sabah’s chief minister, Hajiji Noor, said the same day that such agreements did not mean a project had state approval, according to Bernama, Malaysia’s national news agency.
He said data centre plans would be judged on cost, technology, power and water needs, environmental impact and land use.
The plan
North AIDC managing director Chua Soon Ping said the centre would run entirely on gas-fired generators on site.
Cooling water would be pumped from nearby Salut Bay and desalinated. Staff drinking water would still come from the public supply.
Chua put the cost at about RM4.5 billion before servers, or RM6 billion with them, and said the company would look for outside investors, Overseas Chinese Daily News reported.
It still needs an environmental impact assessment, a gas supply permit and other approvals before building can start.
Where Chinese companies come in
Four of the seven partners are Chinese, Chua said.
Two Shenzhen firms, Yuandong Zhiqi Technology and Weimingsheng Technology, would build sections of 30MW and 20MW. TCL Home Appliances (HK) would supply solar panels, batteries and liquid cooling. Hunan Liyu Gas Power would provide gas generators.
These roles come from the developer. No contracts have been made public.
Why it matters in Sabah
Sabah’s spare water capacity is 1.81 per cent, far below the 10 to 15 per cent the national water regulator recommends, a federal deputy minister told parliament in October, Warta Oriental reported.
In June, the state utility rationed power in several areas after gas supply to some plants was disrupted, Bernama reported.
That is why the self-supply plan is the project’s main selling point, and the impact on power and water will be part of the assessment.
It is not yet known how much water would be taken from the bay, or how it would be returned.
Related reading: Why Grab is taking the lead on AI data centres in Peninsular Malaysia.
Key questions
Has the Sabah AI data center been approved?
The 12 November agreements are memorandums of understanding, and Chief Minister Hajiji Noor said signing one did not mean a project had state approval. The developer says an environmental impact assessment and a gas supply permit are still needed.
How would it get power and water?
On-site gas-fired generators for electricity, and seawater from Salut Bay, desalinated, for cooling. Staff drinking water would still come from the public supply.
Which Chinese companies are involved?
Four of the seven partners, according to the developer: two Shenzhen firms building 30MW and 20MW sections, TCL Home Appliances (HK) for solar, batteries and liquid cooling, and Hunan Liyu Gas Power for modular gas generators. No procurement contracts have been made public.