5 projects tracked1 Contracted4 AnnouncedReviewed

Deployment

Grab and SoftBank’s AI data centre projects in Malaysia

Announced
Joint development agreements signed

Project fields

Operator
Grab leads on the peninsula. SoftBank leads in Sarawak with Grab and PETROS.
Geography
Peninsular Malaysia and Sarawak, Malaysia
Facility
Proposed AI data centres. Tanjung Embang identified for Sarawak. The peninsula site remains undisclosed.
Scale
Proposed seed capital of US$850m on the peninsula and US$1bn in Sarawak. Long-term target of at least 5 GW across both.
Signed
Joint development agreements announced 9 Nov 2026
Evidence
Grab regulatory filing, joint company announcements and an on-record statement by the Sarawak premier.

Status history

2026-11-09
AnnouncedPartners announce joint development agreements for the two projects.
2026-11-10
AnnouncedSarawak’s premier identifies Tanjung Embang as the proposed location.

No further status change recorded · next check first funding disbursement, signed customer or power agreement, or evidence of construction at either site.

Grab and SoftBank have signed joint development agreements for two Malaysian AI data centre projects. Grab leads the project on the peninsula. SoftBank leads the project in Sarawak with Grab and Petroleum Sarawak Berhad (PETROS). Neither project has disclosed a contracted customer or a construction start.

Peninsular Malaysia

Grab would contribute US$650 million of the proposed US$850 million in seed capital. SoftBank would provide US$200 million. Grab plans to bring in other investors as the project grows. The partners’ 9 November announcement gives no site or capacity figure for the peninsula alone.

Sarawak

SoftBank would contribute US$800 million and hold a majority stake. Grab and PETROS would each contribute US$100 million. On 10 November, Sarawak’s premier identified Tanjung Embang as the proposed location. The Sarawak project announcement sets a long-term ambition of 5 GW.

Funding and capacity

Grab’s US securities filing puts the long-term target across both projects at 5 GW or more. It includes Sarawak in that figure. The agreements bind the partners to develop and fund the projects, but each investment still depends on definitive terms. Capital would be released in stages as development and customer contracts progress and closing conditions are met. The partners have yet to disclose how much capital they have paid in or how much capacity either project has brought online.

Related reporting: Why Grab is taking the lead on AI data centres in Peninsular Malaysia.

Sources

  1. Grab Holdings, Form 6-K, 9 November 2026 — binding obligations, staged funding and combined capacity target.
  2. SoftBank Group and Grab, joint announcement, 9 November 2026 — project leads and proposed contributions.
  3. SoftBank Group, Grab and PETROS, Sarawak project announcement, 9 November 2026 — ownership plan and Sarawak capacity target.
  4. Sarawak Public Communication Unit (UKAS), 10 November 2026 — the premier identifies Tanjung Embang.

Entry created 16 November 2026 · Last updated 16 November 2026 · Corrections to corrections@southwardtech.com

Weekly newsletter

The Southward Brief

One email a week on the technologies, companies and industrial shifts reshaping China and the Global South.

Required. Enter a valid email address.

By subscribing, you agree to receive The Southward Brief. You can unsubscribe at any time. Read our Privacy Policy.